Kensington and Chelsea, the smallest yet most densely populated borough in London, embarked on a major transformation in 2023 by separating its Digital, Data, and Technology (DD&T) function from its bi-borough partner. This disaggregation required a new Microsoft Project Online instance, replacing the previous shared IT configuration. Wellingtone, a Microsoft Gold Partner, played a pivotal role in this transformation, supporting the Project Management Office (PMO) at K&C with a rapid deployment of Project Online.


Overview
Customer
Royal Borough of Kensington and Chelsea
Products and Services
Microsoft Project Online
Microsoft Power BI
Industry
Local Government
Key Benefits
- A rapid deployment, from requirements to user adoption in just 12 weeks.
- An iterative approach, focusing on prioritised, manageable delivery.
- Portfolio visibility, status reporting, and resource capacity planning are in place to support change programmes.
- A mutually flexible customer/consultant relationship to support speedy delivery.
Meeting Tight Deadlines Amidst Transformation
Andrew Homan, PMO Manager at K&C, led the creation of a new Project Online environment for K&C in 2023, building on his experience with Wellingtone during the original bi-borough Project Online configuration in 2019. “It was clear that the separation of K&C’s IT services from the bi-borough partner was going to be a disruptive transformational period,” he recalls, “and deploying a new instance of Project Online was a key deliverable in the K&C disaggregation program.”
Before the separation, the bi-borough IT PMO team had established a resource capacity planning capability into Project Online with Wellingtone’s help. “We rolled out that capability for the bi-borough partner in July and December 2022 to enable the leadership team to identify resource shortfalls ahead of the separation of the two councils.” Meanwhile, K&C was preparing for the full disaggregation. “At that point, I stepped over to K&C’s PMO. We had a hard deadline of 31 March 2023 to have the K&C version of Project Online up and running. As part of the disaggregation, we also had a new set of project managers who needed Project Online familiarisation and training during that period. Looking back, our established relationship with Wellingtone and their in-depth understanding of our environment played a key role in meeting that deadline.”
There is no doubt that Wellingtone’s expertise, process, and knowledge of us as an organisation played a pivotal role in getting us to this point so rapidly.
Andrew Homan, PMO Manager
Iterative Approach for Agile Delivery
K&C was also moving towards a more agile working approach, Andrew adds. “That shift in mindset was well aligned to how we handled the Project Online work,” says Andrew. “To make the tight turnaround feasible, we needed to break the project down into pragmatic, manageable milestones. The immediate priority was visibility so that K&C’s new PMO could begin RAG-based status reporting to a Portfolio Review Group that met every two weeks.
Because Wellingtone’s implementation consultant already knew us from the bi-borough period, the requirement-gathering and configuration phase could be accelerated, and our consultant added a lot of value from the beginning. They walked us through a checklist of decisions and kept things as simple as possible. That made it possible for us to make quick decisions so that Wellingtone could go all-out to complete the technical build in just a few weeks (based on their existing client schedule and availability), deploy and test the solution, and then move straight to user training with the minimum of delay.”
For both Wellingtone and K&C, there were capacity challenges, Andrew explains. “The Lead PPM Consultant showed flexibility and goodwill to accommodate the time scales from Wellingtone’s perspective. From our side, we agreed to handle the data migration ourselves manually rather than wait for an available slot in Wellingtone’s schedule. We launched and onboarded the core configuration on time, and our existing relationship with Wellingtone enabled both parties to work collaboratively to get that done.”
Resource Capacity Planning for Strategic Leadership
Wellingtone’s previous work with Andrew on the bi-borough resource capacity planning laid the foundations to introduce a similar capability into K&C’s configuration. “That was a strategic consideration,” Andrew says. “With wider change initiatives ahead, our leadership needed fast visibility across the resourcing pipeline. In the bi-borough environment, we had portfolio visibility and status reporting but no insight into the new K&C project pipeline. We adapted the old bi-borough framework to create K&C’s initial capability and we worked closely with Wellingtone to develop the required system configuration. We didn’t expect resource and capacity planning to yield immediate results–not least because it takes time to fully engage people with the processes behind the data. But, from a standing start, we are building up sound resourcing data and can broadly pinpoint future capacity shortfalls. In my experience, that’s pretty much where we should be at this point after about four months.
Wellingtone provided high-quality training for project managers as well as for our Project Online administrators. Our PMO team is now coaching system users on an ongoing basis to make sure our project managers can use Project Online consistently and confidently. We are also developing a PMO team member to become our central resourcing expert. They will support project managers in using the resource capacity planning module, as well as using Project Online and Power BI more generally. It’s all part of the continuous improvement approach that the PMO is championing.”
The Results: Royal Borough of Kensington and Chelsea
By July 2023, K&C’s Project Online configuration had only been live for four months. But, Andrew says, “We’re up and running. Status reporting is embedded, we’re making progress with resource and capacity planning, and we’re ready to scale up and use the tools to support a big transformational program that’s about to start. We’re also discussing future development in terms of project financial reporting, agile projects, and BAU capacity. I’d say to anyone considering implementing a PPM tool like this, it’s important to get the basic configuration deployed as quickly as possible. Full adoption takes longer but, once the fundamentals are in place, you can start to add value straight away. Plus, you’ll have the foundations in place to build your PPM capabilities in manageable steps. There’s no doubt that Wellingtone’s expertise, process, and knowledge of our organization played a pivotal role in getting us here so rapidly.”